rising sun logo

office (440) 576-8271
fax (440) 576-9705

Press

Press Releases

  • RUNWAY CLOSURE SET FOR MAY 27, 2008

    The Ashtabula County Airport Authority plans to close the runway at the airport on May 27 as part of a three year plan to reconstruct the runway surface.  This first of three phases will install 6 under-drains in the west end of the runway and then cap the surface with a two inch layer of fresh asphalt.  The runway was first built in 1967 and has been resurfaced twice since then. The Authority expects the construction to take 30 days. Koski Construction was awarded The contract in the Fall of 2007 and will work 10 hour days to accomplish the work within the time schedule. 

    The original design did not include drainage under the surface of the runway and the drains along the side of the runway were found to be clogged with silt.  Without an effective drainage system, water accumulates under the runway surface, contributing to a deterioration of the runway surface.  Large and cracks and bubbles are evident in the runway surface and will be eliminated during this rebuilding project. 

    Funds to complete this project come from grants from the Federal Aviation Administration's Airport Improvement Program (AIP).  AIP funding pays 95% of the cost of the program and local funds pay the remaining 5%.  The Robert S. Morrison Foundation is providing funds for the local share through a gift of  $30,737.  The Federal Share of this $614,735 project is $583,998.
  • GIANT SCALE RADIO CONTROL RACES RETURN TO ASHTABULA COUNTY AIRPORT